Pico-Hydro Power Project at Mae Jo village
|
|
|
Contributor (s) |
1. Baan Mae Jo hydro power community enterprise
2. Thai Oil PLC
3. Department of Alternative Energy Development and Efficiency (DEDE)
4. E for E |
Location |
Baan Mae Jo Baan Poa Sub-district Mae Tang District, Chiangmai Province |
Technology |
Turko Turbine (37 kW Capacity) |
Annual Electricity Produced |
27 kWe installed capacity |
Status |
COD February 2014 |
Number of inhabitant |
118 households |
Installation of PV system in Border Patrol Police School
|
|
|
Contributor (s) |
- Energy Regulatory Commission (ERC)
• Implementing Agency
- Department of Alternative Energy Development and
Efficiency (DEDE)
- E for E
|
Location |
1.Ban Por Mue Mae kong Subdistrict, Mae Sarieng District, Mae Hong Sorn Province
2.Ban Jor Pra Kee Mae kong Subdistrict, Mae Sarieng District, Mae Hong Sorn Province
3.Ban Ko Prac Mae kong Subdistrict, Mae Sarieng District, Mae Hong Sorn Province
|
Technology |
Poly-Crystalline 2.6 kW |
Application |
Lighting and Radio Communicotion |
Status |
Started operating in December 2012 |
Pico-Hydro Power Plant at Champathong Temple : Phase II
|
|
|
Contributor (s) |
- Thai Oil PLC
• Implementing Agency
- Department of National Parks, Wildlife and Plant Conservation (DNP)
- Department of Alternative Energy Development and
Efficiency (DEDE)
- E for E
|
Location |
Champathong Muang District, Phayao Province |
Technology |
Turko Turbine (7.5 kW capacity) |
Status |
Started operating in May 2012 |
Border Patrol Police School, Pico-Hydro Power Plant
|
|
|
Contributor (s) |
- Energy Regulatory Commission (ERC)
• Implementing Agency
- Department of Alternative Energy Development and
Efficiency (DEDE)
- E for E |
Location |
- wakalayko Village, Mae La Mard District,
Tak Province
- phobuelakhee Village, Tha Song Yang District,
Tak Province
|
Technology |
Turko Turbine (5.5 kW capacity) |
Status |
July 2011 |
CO2 Mitigation |
6.5 tons/year |
Biogas Projects
|
|
|
Contributor (s) |
- Thai Oil PLC
• Implementing Agency
- Local Economy Learing Center
- Local Government
- E for E
|
Location |
Bann Narej Community at Donjeadee District, Suphanburi Province |
Technology |
Fixed Dome Biogas Plant
(with 100 m3 capacity of each plant) |
Start Operating |
To be completed by March 2011 |
Application |
Cooking stove |
CO2 Mitigation |
94.24 tons/year |
Direct Beneficiaries |
20 Households/plant |
Energy Efficiency Improvement of Miang-Leaves Stoves
|
|
|
Contributor (s) |
- Thai Oil PLC
• Implementing Agency
- E for E |
Location |
Pa Miang village, Mueng Paan district, Lampang Province |
Budget |
Phase 1 : 81 set
Phase 2 : 38 set
|
Direct Beneficiaries |
140 Households |
Hua Puling Pico-Hydro Project : Phase II
|
|
|
Contributor (s) |
- United Nations Development Programme (UNDP)
- Thai Oil PLC
• Implementing Agency
- Local Government
- Department of National Parks, Wildlife and Plant Conservation (DNP)
- Department of Alternative Energy Development and
Efficiency (DEDE)
- E for E
|
Location |
Doi Inthanon National Park, Chiang Mai Province |
Technology |
Cross Flow Turbine (22 kW Capacity) |
Start Operating |
2010 |
Application |
Lighting/television/Satellite Learning |
Annual Electricity Produced |
86,800 kW/year |
CO2 Mitigation |
62.1 tons/year |
Direct Beneficiaries |
2nd Phase : 66 connections
3rd Phase : Extend Electrical Transmission to
Baan Kunya School and 100 Households |
Champathong Temple Pico-Hydro Project
|
|
|
Contributor (s) |
- Thai Oil Plc.
• Implementing Agency
- Department of National Parks, Wildlife and Plant Conservation (DNP)
- Department of Alternative Energy Development and Efficiency (DEDE)
- E for E |
Location |
Muang District, Phayao Province |
Technology |
Reverse pumping 7.5 kW capacity, (Rated Power 5.03 kW) |
Start Operating |
May 2010 |
Application |
Lighting/television |
Annual Electricity Produced |
12,375 kWh/year |
CO2 Mitigation |
14.2 tons/year |
Direct Beneficiaries |
Temple and DNP bunch office |
Thai army 31 Pico-Hydro Project
|
|
|
Contributor (s) |
- Thai Oil Plc.
• Implementing Agency
- Department of National Parks, Wildlife and Plant Conservation (DNP)
- Department of Alternative Energy Development and
Efficiency (DEDE)
- E for E
|
Location |
Klong Lan District, Kampaengpeth Province |
Technology |
Turko Turbine (3 kW installed capacity) |
Start Operating |
April 2010 |
Application |
Lighting/television |
Annual Electricity Produced |
3,153 kWh/year |
CO2 Mitigation |
7 tons/year |
Direct Beneficiaries |
Office of Thai army 31 |
Border Patrol Police School, Pico-Hydro Power Plant
|
|
|
Contributor (s) |
- Energy Regulatory Commission (ERC)
• Implementing Agency
- United Nations Development Programme (UNDP)
- E for E |
Location |
- Kanayjuetha Village, Tha Song Yang District,
Tak Province
- Laypasukhee Village, Mae La Mard District,
Tak Province
|
Technology |
Turko Turbine (5.5 kW capacity) |
Start Operating |
February 2010 |
Application |
Lighting/television |
Annual Electricity Produced |
3,153 kWh/year |
CO2 Mitigation |
6.5 tons/year |
Direct Beneficiaries |
Border Patrol Police School |
Pico - Hydro Projects
In the northern part of Thailand, villages are in mountainous forest areas, most of which has not been electrified. Via the 1st phase of GEM, three community-based hydro projects have been developed, which not only alleviate quality of life but also encourage forest preservation, which is formerly not aware by the local people; as a result, the large areas of tropical rain forest has been destroyed.
Bann Pean Pico-Hydro Project
|
|
|
Contributor (s) |
- Thai Oil Plc.
• Implementing Agency
- United Nations Development Programme (UNDP)
- E for E |
Location |
Jom Thong district, Chiang Mai Province |
Technology |
Turko Turbine (3 kW installed capacity) |
Application |
Lighting/television |
Annual Electricity Produced |
7,153 kW/year |
CO2 Mitigation |
7 tons/year |
Direct Beneficiaries |
10 Households and Temple |
Period |
October 2009 |
Hua Puling Pico-Hydro Project : Phase I
|
|
|
Contributor (s) |
- United Nations Development Programme (UNDP)
- Thai Oil PLC
• Implementing Agency
- Department of National Parks, Wildlife and Plant Conservation (DNP)
- Department of Alternative Energy Development and
Efficiency (DEDE)
- Local Government
- E for E
|
Location |
Doi Inthanon National Park, Chiang Mai Province |
Technology |
Cross Flow Turbine (22 kW Capacity) |
Start Operating |
July 2009 |
Application |
Lighting/television/Satellite Learning |
Annual Electricity Produced |
86,800 kW/year |
CO2 Mitigation |
62.1 tons/year |
Direct Beneficiaries |
1st Phase : 51 connections (47 Households, Temple
and Church, school and DNP bunch office)
2nd Phase : 66 connections
3rd Phase : Extend Electrical Transmission to
Baan Kunya School and 100 Households |
Krae Kee Pico-Hydro Project
|
|
|
Contributor (s) |
- United Nations Development Programme (UNDP)
• Implementing Agency
- Local Government
- Border Green Energy Team (BGET)
- E for E
|
Location |
Tha Song Yang district, Tak province |
Technology |
Water Pump (2.2 kW installed capacity) |
Start Operating |
March 2009 |
Application |
Lighting/television |
Annual Electricity Produced |
12,600 kW/year |
CO2 Mitigation |
2.59 tons/year |
Direct Beneficiaries |
20 Households and Community school |
Ta Po Poo Pico-Hydro Project
|
|
|
Contributor (s) |
- United Nations Development Programme (UNDP)
- Australian Embassy
• Implementing Agency
- Local Government
- Border Green Energy Team (BGET)
- E for E
|
Location |
-Ta Po Poo Village, Tha Song Yang district, Tak province |
Technology |
Water Pump (12 kW installed capacity) |
Start Operating |
January 2009 |
Application |
Lighting/television |
Annual Electricity Produced |
28,800 kWh/year |
CO2 Mitigation |
15.52 tons/year |
Direct Beneficiaries |
60 Households |
Biogas Projects
EforE has constructed 2 biogas projects, located in Saraburi province using pig manure and cow dung, and the biogas produced has been supplied to community as LPG substitution.
Biogas Projects
|
|
|
Contributor (s) |
- United Nations Development Programme (UNDP)
• Implementing Agency
- Local Government
- Economy Learing Center
- E for E
|
Location |
- Kok Toom Sub-district, Nong Khae District,
Saraburi province
- Hinson Sub-district, Kaeng khoi District,
Saraburi province |
Technology |
Fixed Dome Biogas Plant
(with 100 m3 capacity of each plant)
300 pigs and 100 cows |
Start Operating |
February 2009 |
Application |
Cooking stove |
CO2 Mitigation |
185.5 tons/year (94.24 tons/year/plant) |
Direct Beneficiaries |
20 Households/plant |
Training on Solar Cell System Maintenance and Repair under Solar Home Project
The project comprises technician training on the PV system operation and maintenance for local people and local government, by providing tool box for maintenance as well as establishing network within the community in order to support each other and set up the plan In managing and recycling expired battery
Minor repair from manufacturing defect, i.e. missing connector, and broken lighting bulb is made. Installation errors, i.e. installing PV in shady areas, are corrected to achieve the maximum capture of solar energy. Also, the villagers are supported in claiming the warranty
For those whose warranty expires, the project provides technical assistance in refurbishing the solar home systems or replacing the broken components and implementation training guideline.
Training on Solar Cell System Maintenance and Repair under Solar Home Project
|
|
|
Contributor (s) |
- United Nations Development Programme (UNDP)
• Implementing Agency
- Border Green Energy Team (BGET)
- E for E
|
Location |
- Ta Po Poo Village, Tha Song Yang District,
Tak Province
- Krae Kee Village Tha Song Yang District,
Tak Province
|
Direct Beneficiaries |
Lighting/ Laboratory equipment in science room |
Small Wind Turbine
Small Wind
|
|
|
Contributor (s) |
- United Nations Development Programme (UNDP)
• Implementing Agency
- Border Green Energy Team (BGET)
- E for E
|
Location |
Panyaprateep School Small Wind Turbine Project Nakhon Ratchasima Province |
Technology |
2 small wind turbine (with 400 W capacity in each site) |
Application |
Lighting/ Laboratory equipment in science room |
Annual Electricity Produced |
625 kWh/year |
CO2 Mitigation |
0.34 tons/year |
Direct Beneficiaries |
Student in Panyaprateep school/ Laboratory equipment in science room |
Small Wind
|
|
|
Contributor (s) |
- United Nations Development Programme (UNDP)
• Implementing Agency
- Border Green Energy Team (BGET)
- E for E
|
Location |
Small Wind Turbine under Network Renewable Energy project in South Region |
Technology |
4 small wind turbine (with 1 kW capacity of each site) |
Application |
Lighting/television |
Annual Electricity Produced |
2,628 kWh/year |
CO2 Mitigation |
1.41 tons/year |
|
|
|
|
|
|
|
|